Dualization of Shaki Township along Oke – Ogun Poly – Ilesha Baruba Road
Dualization of Shaki Township along Oke – Ogun Poly – Ilesha Baruba Road
9.7km of dualization, awarded 24th September 2020, for 4.8 BLN, Initial contract sum 8.24 BLN by the past administration which was terminated due to non performance
Project Description: The major features of the road being commissioned today include among others, clearing, earthworks, construction of reinforced concrete drain, Access culverts, box culverts, other components include kerbs, reinforced concrete retaining walls, walkways and street lights. The pavement is made up of 150mm thick lateritic sub-base, 150mm stone base with 50mm asphaltic binder course and 40mm asphaltic wearing course